A Healthcare Corporation required an inventory assessment in one of their data centers. This involved five buildings of equipment with multiple floors per building.
The project scope included:
•Onsite project management
•Locating devices from a provided information
•Taking pictures of devices and capturing serial numbers
•Information was placed into electronic folders, which could be sorted for quick access, by the customer
1000+ IT devices
MultiTek Global’s Project Manager worked closely with the customer to identify the scope of the project, and within a tight schedule, MultiTek provided 15 technicians that worked 2 x 12 hour shifts each day to meet the customer’s required deadline.
Project was completed within three weeks and exceeded the customer’s expectations.